UPDATE: Upcoming Utility Work at Avenue Station's Secondary Entrance - July 20*, 2021
Looking for information related to a specific area?
Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).
- Allen Road
- Avenue Road
- Bathurst Street
- Bayview Avenue
- Bermondsey Road
- Birchmount Road
- Black Creek Drive
- Brentcliffe Road
- Caledonia Road
- Chaplin Crescent
- Don Mills Road
- Donlea Drive/Hanna Road
- Don Valley Parkway (DVP)
- Dufferin Street
- Ferrand Drive
- Ionview Road
- Keele Street
- Kennedy Road
- Laird Drive
- Leslie Street
- Lebovic Avenue
- Little Blvd.
- Mount Pleasant Road
- Oakwood Avenue
- Petman Avenue
- Pharmacy Avenue
- Victoria Park Avenue
- Warden Avenue
- Weston Road
- Wynford Drive
- Yonge Street
*Information updated on July 15, 2021*
*Information updated on July 6, 2021*
What Work is Taking Place?
As early as Tuesday July 20, 2021, crews at Avenue Station will be performing wet utility works on the north side of the Secondary Entrance site (refer to map). Construction activities will include concrete breaking (chipping) and directional drilling. Periodically, crews will be required to use the laneway north of the Secondary Entrance to access the site. This work is expected to take place between 7:00 a.m. – 5:00 p.m. for approximately three (3) days.
What to Expect
Noise from construction equipment - including drill rigs, excavators, and hydro-vacuum trucks - can be expected. There will be use of heavy machinery in and around the Avenue Station Secondary Entrance. No utility interruptions are expected as a result of this work. Property access will be maintained.
HOURS OF WORK
- As early as Tuesday July 20, 2021
- This work will take place between 7:00 a.m. – 5:00 p.m. for approximately three (3) days
- This work may be delayed or rescheduled due to inclement weather or unforeseen circumstances
TRAFFIC & PEDESTRIAN DETAILS
- No changes to the current traffic configuration and/or pedestrian routes are expected as a result of this work
- Periodically, crews will be required to use the laneway north of the Secondary Entrance to access the site
- Short-term traffic interruptions within the laneway may be in effect
TRANSIT INFORMATION
- Access to TTC will be maintained at all times
- Please visit www.ttc.ca for more information