UPDATED: North and South Platform Shelter Installation at Ionview Stop - December 14, 2020

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
December 8, 2020

 

     

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Ionview stop north and south platform. North platform installation will begin as early as December 14, 2020 for approximately four days and south platform installation will follow for approximately three days.  

 

What to Expect

A crane will be installed within the guideway work zone to facilitate shelter installation. The structures will be delivered and lifted into place by the crane. Concrete works will also take place as part of shelter installation. Daily lane closures will be required at the work zone. 

 

HOURS OF WORK

Work will begin as early as December 14, 2020 and continue for approximately one week.  

Work may occur from 7:00 a.m. to 11:00 p.m., seven (7) days per week, Monday through Sunday.

Work may be rescheduled due to unforeseen circumstances.

 

TRAFFIC DETAILS

Traffic on Eglinton Ave E will remain one lane in each direction

No left turns travelling eastbound or westbound during the north shelter installation 

No left turns travelling westbound during the south shelter installation 

 

PEDESTRIAN AND TTC DETAILS

There will no changes to existing pedestrian routes or TTC stop locations at the intersection. 

 

OTHER INFORMATION

Due to the nature of this work, at times there will be noise around the work area.

 

Disponible en français.