December 04 2020

Update: Traffic Change at Don Mills Rd and Eglinton Ave E - December 8

Read more »

December 03 2020

Utility Reinstatement Works at Eglinton Avenue East and Mount Pleasant Road - December 5, 2020

 

 

 

What Work is Taking Place?

On Saturday December 5, 2020, crews at Mount Pleasant Station will perform utility reinstatement works on Eglinton Avenue, east of Mt Pleasant Road. To facilitate this work, crews will be required to temporarily close the eastbound lane on Eglinton Avenue between Mt Pleasant and Taunton Roads. Traffic on Eglinton Avenue will be reduced to one lane only, alternating traffic in each direction, while this work takes place.  Read more »

December 02 2020

Demolition of 2020 Bathurst Street at Forest Hill Station - December 2020 to February 2021

2020 Bathurst Street at Forest Hill Station

What Work is Taking Place?

In December 2020, crews will begin to demolish the building at 2020 Bathurst Street (formerly ScotiaBank), located on the southwest corner of Bathurst Street and Eglinton Avenue West.

What to Expect

December 02 2020
December 02 2020

UPDATED: Berwick Road Closure for Concrete Pour - December 5, 2020

 

Orginal Post: November 27, 2020

Updated on December 2, 2020

 

 

 

What Work Is Taking Place?

On Saturday December 5, 2020, Berwick Avenue will be closed at Yonge Street while a concrete pour takes place at the Berwick Portal site.  The concrete will form part of the portal walls.  A concrete pump will be placed on Berwick Avenue and several concrete trucks will enter the site each hour.

  Read more »

December 01 2020

North and South Platform Shelter Installation at Ionview Stop - December 8, 2020

 

     

 

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will install permanent shelters at the Ionview stop north and south platform. North platform installation will begin as early as December 8, 2020 for approximately four days and south platform installation will follow for approximately three days.  

 

What to Expect Read more »

November 30 2020

Upcoming Concrete Pour at Eglinton Avenue and Yonge Street - December 3, 2020

 

Orginial Post: November 27, 2020

UPDATED on November 30, 2020

 

What Work Is Taking Place? Read more »