UTILITY CROSSING AT DON MILLS ROAD, EAST SIDEWALK

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

 
June 12, 2020

UTILITY CROSSING AT DON MILLS ROAD, EAST SIDEWALK

 

WHAT WORK IS TAKING PLACE?

As part of construction of the future Science Centre Station for the Eglinton Crosstown LRT, crews will be completing a hydro utility crossing on Don Mills Road. Construction activities will take place on the east side of Don Mills Road between Eglinton Avenue East and Wynford Drive on June 15, 2020. To ensure pedestrian safety, the sidewalk on the east side on Don Mills will be closed. Signage will be installed directing pedestrians to the sidewalk available on the west side of Don Mills Road. There will be no impacts to existing TTC stop locations. 

WORK AREA MAP


HOURS OF WORK  

  • Work is expected to take place on June 15, 2020 between 9:00 a.m. and 4:00 p.m.
  • The contractor may not always work during the permitted hours but may do so at its discretion. Work may be rescheduled or extended due to weather conditions or unforeseen circumstances.

WHAT TO EXPECT  

  • Crews will be performing a hydro utility crossing on the east side of Don Mills Road, north of Eglinton Avenue East.
  • The sidewalk on the east side on Don Mills will be closed between Eglinton Avenue East and Wynford Drive. Signage will be installed directing pedestrians to the sidewalk available on the west side of Don Mills Road.
  • East-west pedestrian crossing is available at Wynford Drive.  
  • There will be no change to the current traffic configuration associated with this work.  
  • Noise and dust from construction equipment and vehicles can be expected. 

Transit Information

  • There will be no impacts to existing TTC stops.
  • Visit www.ttc.ca for more information.