Utility Relocation

Looking for information related to a specific area?

Choose an intersection from the drop down list to view the latest news and construction updates. Intersections are listed alphabetically (with Eglinton as the main cross-street).

Syndicate content
 
November 012017

Changes to the Driveways at 2360 Eglinton Avenue East: Stage 1

In Support of Upgrades to Water Infrastructure for the Eastern End of the Eglinton Crosstown LRT Line

Beginning as early as Monday, November 6, 2017 for approximately four (4) weeks, driveways at 2360 Eglinton Avenue East will be modified to support construction of the Crosstown LRT. Work will be done in two stages, each stage lasting approximately two (2) weeks.

Please see image below showing changes to access to 2360 Eglinton Avenue East during Stage 1 of this work.

What Work is Taking Place? Read more »

October 272017

Overnight Watermain and Sanitary Installation at Kennedy Station

Originally Issued: October 27, 2017

Updated and Reissued: November 1, 2017

What Work is Taking Place? Read more »

September 202017

Preliminary Notice to Businesses and Residents: Upcoming Power Outage Between Birchmount and Kennedy

What Work is Taking Place?

Since June 2017, crews have been upgrading and relocating existing hydro utilities in the area located just west of Birchmount Road to Kennedy Road in the vicinity of Eglinton Avenue East. To complete this work, a Hydro outage is required.

Hours of Work Read more »

March 312017

LOW WATER PRESSURE NOTICE: Watermain Investigation Work

What Work is Taking Place?

On April 3, 2017, crews will begin subsurface utility engineering (SUE) investigation of a large 900mm watermain in the Eglinton Avenue West and Chaplin Crescent area.  The watermain will be exposed to determine the utility and ground conditions in advance of wet utilities relocation.  Most of the work will take place within the existing traffic staging at Chaplin Crescent and Eglinton Avenue West. Read more »