July 032018

Wet Utility Upgrades along Surface Section of the Eglinton Crosstown LRT: Victoria Park to Eglinton Square

What Work is Taking Place?

As part of construction of the future surface alignment for the Eglinton Crosstown LRT, crews will be upgrading and relocating wet utilities along Eglinton Avenue between Victoria Park Avenue and Eglinton Square.

Starting as early as July 3rd and lasting approximately four (4) weeks, crews will install new pipes, and replace manholes and catch basins. This work supports the upgrade of water infrastructure across Eglinton Avenue East for the future Crosstown surface stops. Read more »

June 252018

Reissue: Hydro Utility Relocation between Bermondsey and Birchmount for the Eglinton Crosstown LRT

 

What Work is Taking Place?

The Eglinton roadway is changing as work continues to prepare for the construction of the surface section of the Eglinton Crosstown LRT that will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level.

Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be located.  Read more »

June 182018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park for June 14, 2018. You can see the presentation here:

Read more »

May 072018

Brentcliffe - Victoria Park Construction Liaison Committee Meeting

The presentation for the construction liaison committee meeting of Brentcliffe - Victoria Park for the month of May 2018 can be viewed here:

Read more »

April 062018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on April 5, 2018. You can see the presentation here:

Read more »

March 292018

Central-East Open House (Laird Station to West At-Grade (Sunnybrook - O'Connor Stops)

Thank you for attending the open house about Laird Station to West At-Grade (Sunnybrook - O'Connor Stops) on March 28, 2018.

For those of you who missed it, the presentation is here: Read more »

March 282018

Clearing, Grubbing, and Pruning between Don Avon Drive to Victoria Park Avenue in Preparation for Construction of Surface Stops

As our constructors get ready to ramp up construction activity at the surface section of the Eglinton Crosstown LRT project, clearing, grubbing, and pruning and protection activity continues as part of preparatory work. This activity commenced two years ago and is done on an ongoing, as-needed basis to support the construction of the Eglinton Crosstown Light Rail Transit Project (ECLRT). All works will be carried out with the approvals and cooperation of the responsible authority. Read more »

March 082018

Bell Utility Relocations Between Gervais Dr & Victoria Park Ave

What Work is Taking Place?

The Eglinton roadway is changing as work continues to prepare for the construction of the surface section of the Eglinton Crosstown LRT that will run down the centre of Eglinton Avenue East in dedicated transit lanes at street level.  Setting up the construction work zones in the roadway will require changes to how car and truck, bus, and pedestrian traffic flows along Eglinton Avenue East and the associated intersections where future stops will be l Read more »

March 022018

Brentcliffe - Vctoria Park Construction Liaison Committee Meeting

The construction liaison committee meeting of Brentcliffe - Victoria Park was held on March 1, 2018. You can see the presentation here:

Read more »