August 21 2017

UPDATED: Dewatering System at Avenue Station

Updates: August 21, 2017
Latest Issue Date: May 15, 2017
Original Issue Date: April 17, 2017

 

What Work is Happening? Read more »

August 21 2017

Trailer Move at Caledonia Station

What work is taking place?

On August 22 and 23, crews will relocate a trailer at the Caledonia Station site to continue deep excavation.  Short-term lane reductions will be in effect.  Pedestrian access will be maintained.

Timing Read more »

August 18 2017

Update: Tunnel Concrete Pour for Laird Station

To progress construction at Laird Station and prepare for upcoming mining works, crews will be drilling from the right of way surface into the completed TBM tunnel to fill portions of the tunnels with concrete.

Hours of Work  Read more »

August 11 2017

Toronto Hydro-Electric System Limited (THESL) Relocation Work at Kennedy Station

What Work is Taking Place?
Crews will relocate and upgrade existing overhead hydro utilities between the West Service Roads to the East Service Roads of Eglinton Ave East in preparation for construction of the Kennedy Portal and the Kennedy LRT Station.
August 10 2017

Overnight Preparatory Works for Sewer Lining at Avenue Station

Overnight Preparatory Works for Sewer Lining at Avenue Station

In advance of upcoming mining works at Avenue Station, crews must install sewer linings to the existing sewer infrastructure in the vicinity of the station on Eglinton Avenue West between Braemar Avenue and Lascelles Boulevard. Work also includes one location at Avenue Road and Burnaby Boulevard, as well as one location on Highbourne Road and one on Oriole Parkway. Read more »

August 10 2017

Avenue Station Secondary Entrance Sound Wall

Original Issue Date: July 6, 2017
Re-issue Date: August 10, 2017 

What Work is Happening?

Starting as early as Friday, August 11, work will begin to construct a sound barrier wall at the north side of the secondary entrance. This wall is engineered for maximum sound reduction and will be in place until construction of the station nears completion.

Hours of Work/ What to Expect Read more »

August 10 2017

Drill Move at Forest Hill Station

What Work is Taking Place?

On Thursday, August 10, crews will move the drill rig located at the Secondary Entrance east to the Main Entrance in advance of piling at the Main Entrance.  The drill rig will exit the Secondary Entrance and travel east along Eglinton Avenue West, crossing Bathurst Street, over to the Main Entrance located on the northeast corner of Eglinton Avenue and Bathurst Street.  

During the move, traffic at the intersection will be stopped for approximately 15 minutes. Read more »