Watermain Valve Installation and Servicing Work at Fairbank Station

Watermain Valve Installation and Servicing Work at Fairbank Station 

 

What work is taking place? Read more »

May 16 2017

Shoring and Utilities Relocation in the Roadway at Fairbank Station

 

What work is taking Place?

Since fall 2016, crews have been conducting support of excavation work (also known as shoring) at the Main Entrance and Service Building sites of the future Fairbank Station.  In mid-May 2017, crews will begin shoring of the station box, as well as wet utilities relocation, starting on the north side of Eglinton Avenue East.  Read more »

May 16 2017

UPDATED: Dewatering System at Avenue Station

 

UPDATED: Dewatering System at Avenue Station Read more »

May 15 2017

Update: Hydro Ductbank Connections Continue at Science Centre Station

What Work is Taking Place?

As part of ongoing utility relocation work for the future Science Centre Station, crews will be conducting ongoing, intermittent hydro infrastructure work at the intersection of Don Mills Road and Eglinton Avenue East beginning as early as mid-May.

Timing
Read more »

May 12 2017

Update: Tunnel Concrete Pour for Laird Station

To progress construction at Laird Station and prepare for upcoming mining works, crews will be drilling from the right of way surface into the completed TBM tunnel to fill portions of the tunnels with concrete.

Hours of Work  Read more »

May 10 2017

Traffic Reconfiguration at Don Mills & Eglinton: Nighttime and 24 Hour Weekend Work May 11 – 14

What Work is Taking Place?

As part of the continued support of excavation works and utility relocations for the future Science Centre station, traffic staging at the intersection of Don Mills Road and Eglinton Avenue East will be changing as early as May 11, 2017.  Read more »