What's New?
Overnight OCS Cable Installation on Eglinton Ave at Don Way, Swift Dr/Credit Union Dr, Sloane Av/Bermondsey Rd
What Work is Taking Place?
Crews will be installing OCS (Overhead Catenary System) cables along Eglinton Avenue East between Don Way (NE ramp, S-WN ramp), Swift Dr/Credit Union Dr, and Sloane Ave/Bermondsey Dr. Overhead catenary is the system installed overtop of the rails of a light rail system, to provide operational power to the LRVs (Light Rail Vehicles). Installation will take place January 11-22, 2021 between the hours of 9:00 p.m. and 6:00 a.m. Read more »
Avenue & Chaplin CLC - Presentation Deck - January 6, 2021
Construction Liaison Committee of Avenue & Chaplin was held on January 6, 2021. You can see the presentation here.
Fairbank & Oakwood Construction Update - January 6, 2021
The following construction update for Fairbank and Oakwood stations has been updated as of January 6, 2021. You can view the presentation here:
Update: Crane Footing Removals at Oakwood Station - January 4, 2021
What Work is Taking Place?
Disassembly and removal of the overhead gantry crane is complete at Oakwood Station. Completion of this work allows crews to begin removing the gantry crane footings from the station's Main Entrance site. Read more »