UPDATED MAY 30, 2022
Traffic Configuration Change at Bayview Avenue and Eglinton Avenue East
What Work is Taking Place?
As early as Tuesday, June 7, 2022, a new traffic configuration will be implemented at Bayview Avenue and Eglinton Avenue East. Traffic on Bayview Avenue will shift to the east side of the street and construction will move to the west side. The crosswalk on the west side of the intersection will close, and the crosswalk on the east side of the intersection will reopen. The northbound right turn from Bayview Avenue onto Eglinton Avenue East will be reinstated. This configuration will remain in place until approximately late July 2022.
What to Expect
Overnight noise can be expected while the traffic changes are being implemented. Utility reinstatement and road and sidewalk restoration works will take place on the west side of Bayview Avenue. Expect delays while traveling through the intersection. Concrete barriers, fencing, and wayfinding signage will be in place to delineate the work zones.
HOURS OF WORK
- As early Tuesday, June 7, 2022
- This traffic configuration will remain in place until approximately late-July 2022
- Overnight work may be required to implement the traffic changes
- This work may be rescheduled due to inclement weather and/or unforeseen circumstances
TRAFFIC DETAILS
- Traffic on Bayview Avenue will shift to the east side of the street and construction will move to the west side
- The northbound right turn from Bayview Avenue onto Eglinton Avenue will be reinstated; all other turn restrictions will remain in place
- One lane of traffic in each direction will be maintained on Bayview Avenue and Eglinton Avenue East
PEDESTRIAN DETAILS
- The crosswalk on the west side of the intersection will close
- The crosswalk on the east side of the intersection will reopen
- All other pedestrian routes will remain the same
TTC IMPACTS
- Access to TTC will be maintained at all times.
- Please visit www.ttc.ca [1]for more information.